Camp Build Schedule

Sunday In Reno

  • Pick up Truck
  • Walmart
  • Winco
  • Home Depot

Monday

  • Monday Team Arrives on Playa before Noon
  • Placers take us to our village
  • Monday Team maps out the ground, placing flags to delineate the borders of each camp in the village (DK Lead)
  • Gerlach containers are delivered sometime after 2:00 PM and placed by the early arrival crew
  • Monday Team unpacks, sets up their shade structures and tents and general pods and otherwise settles in.


Tuesday

  • Team gets all stuff from the NY Container early in the morning
  • Team builds the common shade area and the living room areas of the camp
  • Team builds the kitchen out of three carports
  • Team unpacks and inventories the containers

Wednesday

  • Wednesday Team arrived on playa before noon
  • Wednesday Team unpacks, sets up their shade structures and tents and general pods and otherwise settles in.
  • Container Top Dance Platform and Stairs and DJ Booth (Boris Lead)
  • Arch Build Starts (Isa Lead)
  • Assemble Playatech furniture (Josh Lead)

Thursday

  • Reformata Build Showers
  • Build evap ponds
  • Continue Container Top Dance Platform and Stairs and DJ Booth (Boris Lead)
  • Lamassu Build (Kimmy)
  • Canvas on arch, vines on arch and container
  • Canvas on Containers (Lori Lead)

Friday

  • Friday Team arrived on playa before noon
  • Friday Team unpacks, sets up their shade structures and tents and general pods and otherwise settles in.
  • Dome Build (Brandon Lead)
  • Finishing frontage projects
  • Build Fence from fence to end of frontage (Gavin Build)


Saturday

  • Build tress shade structure for dance area (Alex Funk Lead)
  • Sound Build (Alex Funk Lead)
  • Finish kitchen install, unload kitchen truck
  • Rope Lighting for container top and common shade area (Leon M Lead)
  • Steps for runway

Sunday

  • Team sets up the racks inside the dome ([Build Key]
  • Team sets up flags
  • Team cleans up all the tools and repacks the containers
  • Team completes any and all other tasks that have to be done for the build
  • Special surprise planned for the build crew!